Trying to fit in an entire kitchen remodel before the holidays would be incredibly stressful, but tackling a smaller project is still very doable and, depending on what you’re looking to do, could be done in time for Thanksgiving or Christmas. Here are a couple of ideas for what remodeling projects could be reasonably done before the holidays without too much stress.
Backsplash
Lead time: 1-2 weeks
Demolition + installation: 2-3 days
The sky is the limit with backsplashes. A simple subway tile backsplash can be installed in a day, but something like an intricate mosiac will take a little extra time.
Countertops
Lead time: 2 weeks for templating and fabrication
Demolition + installation: 2-3 days
What better way to get ready for the holidays by getting a new countertop to cook on?
New Flooring
Lead time: 1-2 weeks
Demolition + installation: 2-3 day
Hallmark Floors hardwood, engineered wood, and vinyl are all great options for new flooring. We carry their full line in our showroom and there is something for every style and budget.
Paint a Room
Time: 3-4 days depending on room
A fresh coat of paint can be a great and inexpensive way to change your home. Our designers can help you with color choices, too!
New Vanity
Lead time: 1 day on stock cabinets, 2 weeks on semi-custom
Demolition + Installation: 1 day
Kitchen Cabinets
Lead time: 1 day for stock, 2 weeks for semi-custom
Demolition + Installation: 3-4 days